§ 42-46. Pre-excavation facilities location.  


Latest version.
  • In addition to complying with the requirements of Minn. Stats. ch. 216D ("One Call Excavation Notice System"), before the start date of any right-of-way excavation, each registrant that has facilities or equipment in the area to be excavated shall mark the horizontal placement of all said facilities. Any registrant's facilities or equipment that are in the area of work shall notify and work closely with the excavation contractor to establish the exact location of its facilities and the best procedure for excavation to protect the safety of workers and right-of-way users and other utility users. If the utility is not at the approved location, it shall be exposed at the permittee's expense or by the city upon written notice to the permittee. The city may, upon said notice, locate said utility at the permittee's expense.

(Ord. No. 02-01, § 1(3-6.24), 4-24-2002)